To date we have removed 680 tons of steel from the plant. We are behind schedule a month an a half into the project with a full crew, but improving everyday. No accidents and everyone is starting to learn to read metal. Most of all, we are beginning to work as a team. This has proven most valuable in the safety part of the job.